Maintenance, Construction Updates

Posted on: January 5, 2018

[ARCHIVED] Bluebonnet Avenue Project

road construction

Construction Update on Bluebonnet Avenue

  • Setting up forms and preparing for concrete pour on east side of Bluebonnet Avenue from Marshall Avenue to St. Augustine Avenue. 
  • Pour concrete on east side of Bluebonnet Avenue from Marshall Avenue to St. Augustine Avenue.
  • Excavate and set forms on east side of Bluebonnet Avenue from St. Augustine Avenue to Gulfway Drive and inside lanes at DeQueen Boulevard intersection. 

Future Outlook

  • Continue setting up forms and tying steel for east side of Bluebonnet Avenue from St. Augustine Avenue to Gulfway Drive and inside lanes at DeQueen Boulevard intersection.
  • Working on all side street transitions on east side of Bluebonnet Avenue.
  • Prepare and finish full depth concrete repair on east side of Bluebonnet Avenue near 19th Street.